(April 1, 2022 through December 31, 2023)
Project To End of Q4 2023 |
|
---|---|
Procurement | 63% |
Engineering | 84% |
Underground development/construction | 60% |
Surface construction | 41% |
Total Project | 60% |
(April 1, 2022 through December 31, 2023)
Project To End of Q4 2023 |
|
---|---|
Procurement | 63% |
Engineering | 84% |
Underground development/construction | 60% |
Surface construction | 41% |
Total Project | 60% |
Notes to Table
(April 1, 2022 through December 31, 2023)
Millions of U.S. dollars | Project To End of Q4 2023 |
---|---|
Project expenditures per 2022 Technical Report | $848.4 |
Adjustment for underspend in Q1 2022 | $26.1 |
Total project expenditures | $874.5 |
Total project expenditures incurred to date | ($491.0) |
Remaining project expenditures | $383.5 |
Committed expenditures (inclusive of total project expenditures incurred to date) | $731.1 |
Uncommitted expenditures | $143.4 |
Notes to Table
February 2024
Media Luna Construction Progress
January 2024
Media Luna Construction Progress
January 31, 2023
Supporting communities South of the Balsas River through the Media Luna Project
April 1, 2022
Media Luna Project Overview: Underground Animation
April 1, 2022
Media Luna Project Overview: Plant & Surface Animation